Project’s Value – $2,155,000
SPS Pump Station Upgrade / Midge Point and Seaforth Re-Chlorination Facilities
Barnes Creek Temporary Sewer Bypass

Jan 2015 – Oct 2016

Upgrade of 4 x Sewerage Pump Stations including by-passing works, new pipework, pumps and lids, new switchboards and commissioning of refurbished pump station. Site civil works including new concrete pits, gravel hardstand areas and site fencing.

Installation of new CL2 Gas re-chlorination equipment and facilities at Seaforth and Midge Point.

Temporary installation of 570 meters of 450mm poly pipe across Barnes Creek Bridge to allow